By Jason Charles Guck, Business Development, Delta Edge CI
PJM ran on about two-thirds of its fleet this month.
That is the number worth carrying into November, and it did not come from a heat wave or a storm. It came from a mild October.
I wrote on October 13 about the federal emergency order that opened that week, while it was still in force. What follows is what the operating data showed afterward, and what four states have done since. The order was the headline. The fleet availability figure is the part that actually matters.
What the week actually looked like
Across the week of October 13, more than 61,000 MW of generation was out of service across PJM. On preliminary figures, roughly 15,000 MW of that was unplanned. More than two-thirds of the total was planned maintenance or construction, which is what an autumn outage season is for.
The result, according to David Souder, PJM’s executive director of system operations, was a grid running with only about 66 percent of its generating fleet available.
PJM worked with generators to return about 10,000 MW to service. It did not push further, and the reason is the part operators should sit with. Souder indicated that cancelling more planned outage work would risk leaving those facilities unprepared for winter.
Read that as a trade rather than a decision. The system can borrow capacity from the maintenance calendar in October, and the loan comes due in January. There is no version where it is free.
The statistic that should end the summer-only assumption
Through October 14, PJM had activated demand response on nine days in 2026.
Across the entire 2015 to 2024 period, it activated demand response on eight days.
One year has now exceeded a full decade. Widen the window slightly and PJM’s own framing is starker: 15 activation days across 2025 and 2026 combined, against eight days in the ten years before them.
Demand response customers are paid in advance to reduce electricity use when the system is stressed. PJM called on them on both October 13 and October 14, during unseasonably warm weather rather than extreme weather.
A Department of Energy emergency order, which Souder described as the ninth DOE order of the year, also allowed PJM to direct large consumers including data centers to run backup generation if it came to that. As of PJM’s update, that authority had not been used.
Note what did get used and what did not. The backup generation authority stayed in the drawer. Demand response was called twice in two days. The tool that worked was the one where customers had already agreed to move.
PJM coordinates the grid for all or parts of 13 states and the District of Columbia. When capacity is this tight in a shoulder month, capacity costs follow, and the argument over who pays for them is being settled state by state right now.
Indiana: data center money arriving on household bills
On October 28, NiSource’s NIPSCO announced a $57.5 million credit for existing electric customers, funded through data center development. Subject to regulatory approval, the average residential electric customer would receive about $5 a month for 18 months, roughly $90 in total, beginning about 30 days after approval.
That sits on top of $1.75 billion in customer credits expected from previously announced agreements with Amazon, Alphabet and Microsoft. The first of those credits is expected to begin in the first quarter of 2027 and ramp up from there.
The mechanism is the interesting part. Under NiSource’s structure, large load customers fund the infrastructure built to serve them, and a portion of the contract revenue returns to existing customers. That is closer to cost causation than most states have managed, and it is being done through contract terms rather than through a rate case.
One caveat belongs with it. The announcement covers electric customers. NIPSCO’s residential base is largely gas, and gas customers were not included.
The question every other state now has to answer is whether a credit after the fact is the right design, or whether large loads should simply carry their full cost up front so households never take it on in the first place.
Oklahoma: two dockets, and only one of them waited
Oklahoma is running two separate proceedings that are easy to confuse, and the difference between them is instructive.
The first is OG&E’s large load tariff case, the one that decides how data centers are priced. Its hearing was scheduled for November 3 and has been moved to January 12, 2027. I covered that delay in the piece on data centers as a ballot issue. The question of who pays for large load growth now gets answered well after voters have gone home.
The second is PSO’s base rate case, and that one is on the calendar for Tuesday, November 3. The Corporation Commission is set to vote on a proposed order that commissioners have described as carrying a minimum total bill increase of 1.5 percent across all customer classes, with the residential impact potentially landing in the high 1 percent to mid 2 percent range.
Here is the piece worth knowing if you are a PSO customer. Interim rates took effect on July 1, 2026, under the rule that allows them when the commission has not acted within 180 days of a filing. If the final order lands below the interim rate, PSO must refund the difference, and by law that refund has to be completed within 90 days of the new rates taking effect. Customers do not have to file anything to receive it.
Two dockets, one state, one regulator. One moved past the election and one landed on it. Neither timing was set by a customer.
MISO: if you promise to cut load, you have to deliver
On October 23, FERC largely approved tougher non-performance penalties for load modifying resources in MISO. That category covers demand response and behind-the-meter generation, which means it covers a large number of commercial and industrial operators directly.
The new rules take effect June 1, 2027, for the 2027/2028 planning year. MISO had originally asked for June 1, 2026, and protesters argued that would apply retroactively to resources already registered. The date moved.
In MISO’s own materials, a complete performance failure means delivering less than 25 percent of the amount the participant acknowledged when the scheduling instruction was issued. A partial failure is delivering at least 25 percent but still falling below the tolerance band, which is the greater of 0.1 MW or 12 percent of the acknowledged amount.
The consequences stack:
- A complete performance failure will generally disqualify the resource for the remainder of the planning year, unless it fully performed in response to at least one scheduling instruction in the same season.
- Two complete failures in a single season can mean exclusion from the following year’s capacity auction.
- A resource disqualified within three years of a previous disqualification can be barred from the auction for the following three planning years.
FERC also ordered compliance filings, including a 30-day window for MISO to resolve an inconsistency in how two of the penalty types are calculated, so the fine print is not final yet.
The principle behind it is hard to argue with. Capacity that does not show up in an emergency was never capacity. It was a line in a spreadsheet.
The practical reading for an operator is narrower and more urgent. If your site carries a demand response obligation, the gap between what you registered and what you can actually shed on a weekday afternoon has become expensive in a way it was not before. That gap is usually discovered during a call, which is the worst possible time to find it.
Vermont: a small utility, a large percentage
The Town of Hardwick Electric Department has filed for an overall rate increase of 14.11 percent, docketed with the Vermont Public Utility Commission as case 26-1677-TF. A public hearing is scheduled for November 17 at 7:00 p.m. by videoconference, following a presentation by the Department of Public Service at 6:30.
The filing requested an effective date of October 1 for service rendered on or after that date. The increase is still under review and is not a final, settled charge. Local reporting ties the request to higher power and depreciation costs and to a plan to begin building an operating reserve.
Hardwick serves a few thousand customers. The cost pressure is the same one the large grids are carrying. The difference is that there are fewer customers to spread it across, which is why small utilities tend to post the largest percentages.
The bottom line
PJM at 66 percent availability in October. Demand response called on nine days this year after eight days in a full decade. A federal order holding backup generation in reserve. Credits in Indiana, a vote in Oklahoma, tougher performance rules in MISO, and a 14 percent filing in Vermont.
That is one story told in five places. The grid is tight, large loads are growing faster than the structures built to allocate their cost, and somebody has to pay for reliability.
Notice the direction all five are pointing. Indiana is returning money to customers because large loads paid in. MISO is raising the cost of a promise you cannot keep. PJM is paying customers to use less because the alternative is worse. Every one of those is a system putting a price on load that can move.
That is a straightforward signal for anyone running a building. Load you do not draw is the only load nobody can reprice. Load you can shed on request is becoming worth more, and load you promised to shed but cannot is about to cost more.
Three things are worth doing before winter rather than during it. Pull your interval data from October 13 and 14 and see whether your site moved at all. Find your current capacity obligation and confirm somebody on site can actually execute it. Separate capacity and delivery from commodity in your 2027 budget, because that is where the pressure is arriving.
That is the work we do at Delta Edge CI. A zero-cost energy analysis that finds the waste, separates usage from rate, and funds the fix out of the savings rather than out of your capital budget.
These are live proceedings. The NIPSCO credit, the PSO order, the Hardwick increase and the MISO compliance filings were all pending at publication, and none of them is final. Operating figures are PJM’s as reported, including preliminary outage data. Confirm anything that affects a budget against the current docket before building a number on it.